Ben Avon Paving Details

Independent Enterprises contractors will be begin Ben Avon’s milling and paving project on Monday, August 27th starting at 7am.  They are expected to start on the west side of Ben Avon at Rostrevor and work their way east through the week on the designated streets listed at http://benavon.com/traffic-and-road-updates/.  The milling is expected to take approximately one week, weather and other constraints permitting, then the complete paving process will take another couple of weeks.

Working Hours will be 7:00am to 5:00 pm Monday thru Friday
(Rain days will be made up on Saturdays)
Independent Enterprises will strive to keep the inconvenience to a minimum.
Should you have any questions or require additional information, please contact the Superintendent, Anton Zupancic at 412.639.6946 or the Project Manager, Rich Roscoe at 412.287.8851.

There will be no parking on the affected streets during this construction where signs are posted. All vehicles parked on the affected streets will be towed at the owners’ expense. Thank you in advance for your anticipated cooperation.

During the paving project, two major routes into the Borough will be closed at times: Dickson Avenue and Brighton Avenue. There will be times when one of these main routes will be limited or closed (great care will be made to ensure they are not closed at the same time). Along with the contractor, we will do our best to alert all residents of when these roads will be closed or limited.

For Ben Avon specific questions you may call the Ben Avon Public Works department at 412.761.5311.

As always, thank you so much for your patience and understanding as we continue to restore Ben Avon for the future.

http://benavon.com/traffic-and-road-updates/